Article Index

RBM05-Blue Mountain Sportsmen Center Rehabilitation II

  • Design of lead remediation at shooting ranges nearing completion.

RBM06-Blue Mountain Reservation Dam Project

  • Rehabilitation construction of dams complete.

RBR02-Bronx River Parkway Reservation-Scout Field

  • Improvements to the grounds complete.

RBR04-Bronx River Parkway Reservation

  • Construction underway on the pathway connection from Midland Avenue south to the Oak Street loop.

RBR07-Bronx River Pathway Reconstruction

  • Design underway for 1st phase of pathway improvements from Kensico Dam Plaza south to Green Acres Avenue.

RCC17-County Center Facility Improvements

  • Design underway for flood mitigation improvements and back-up generator.

RCL01-Cranberry Lake Preserve Nature Center

  • Design nearing completion for a new nature center.